Conventional method
Materials required
(1 footing):
- 4 Stakes (forming)
- 16 D nails
- 8’ to 12’ of lumber (footing
form) 2X12’s or 2X10’s or
2X8’s (Depending on footing
requirements)
- 1”X4” lumber for braces and
stakes
- 8 D Nails
- 1” roofing nails or 1” wood
screws
- Sonotube® form
- Concrete
- Rebar #4 or #5
- Rebar stand (optional)
- Rebar ties Tools & equipment required:
- Shovel, hand saw, hammer,
square
- Level, backhoe, electricity,
saw horse
- Circular saw, tape measure,
pry bar, trowel
- Sledge hammer |
Labor required - Day 1
• Excavate/dig hole with shovel
or backhoe.
• Cut wood into 4 pieces and nail
together to form a box.
• Place box into excavated hole.
• Level.
• Stake box into excavated hole.
• Set rebar on rebar stand.
• Cut/bend rebar to L shape.
• Insert rebar in footing to receive
column.
• Screed footing. |
Labor required - Day 2
• Remove/strip wood forms and
stakes at footing.
• Secure strapping cleats to wood
footing form to receive Sonotube
form.
• Cut Sonotube form to required
height.
• Connect/secure Sonotube form
to cleats with 1” screws.
• Plumb/level Sonotube form as
you backfill around tube with
shovel or backhoe.
• Pour concrete into form.
• Finish top of concrete.
• Insert brackets or anchor bolts
at top of Sonotube form as
required. |
Labor required - Day 3 • Remove bracing.
• Cut off part of Sonotube form
visible above ground. |
|
TubeBase® method
Materials Required (1 Footing):
- TubeBase
- Construction tube
- 1” screws
- Rebar (if required)
Tools & equipment required:
- Shovel, hand saw, battery
powered drill, level, screw
driver, backhoe |
Labor required - Day 1
• Excavate/dig hole with shovel
or backhoe.
• Cut Sonotube form to required
height.
• Set Sonotube form on Tubebase
to determine proper fit.
• Cut off excess plastic at top of
wedges/rings being used.
• Screw Sonotube form to
Tubebase with 4 1” screws.
• Install rebar if required.
• Place combined Tubebase &
Sonotube form in hole on
undisturbed soil or 4” to 6” of
crushed stone.
• Plumb/align prior and during
backfilling.
• Brace top of Sonotube form if
required (above ground).
• Backfill - Avoid dropping rocks or
heavy soil directly on Tubebase.
• Invert another Tubebase and use
as funnel when pouring concrete.
• Insert brackets or anchor bolts at
top of Sonotube form as required. |
Labor required - Day 2
• Remove bracing if required.
• Cut off portion of form visible
above ground. |
Labor required - Day 3 NONE |
|